Public Utilities Department Water and Sewer Division crews will work four nights a week, Sunday nights through Wednesday nights from 6:00 p.m. until 7:00 a.m. the next mornings, on the project. Closed roads will re-open during the day. Update: Day work is taking place until approximately July 17 (weather permitting) for concrete and asphalt installation and will result in some daytime lane closures. Work will also continue during the evening as described. The project is currently ahead of schedule.